hall: 3,240 sqm, office: 1,840 sqm
hall: 62/54/9.5 m. office: 14.5/41.5/10.5 m
Logistics building, Office buildings
turnkey
April 2013 - Oct. 2013
In its first construction project for Jungheinrich, BREMER AG is tasked with realising two distribution centres at the same time. This newbuild project is for a service centre with warehouse and workshop areas as well as an adjoining 3-storey administrative building realised as a precast reinforced concrete structure. The hall has a sheet metal facade. The roof consists of trapezoidal sheeting with insulation and impermeable membrane. The facade of the administrative building is a sheet metal curtain facade with aluminium strip windows. The offices have a solid ceiling with insulation and impermeable membrane. The adjoining office building is linked to the hall by a connecting structure and showroom. The heating and cooling requirements of the building are met by geothermal energy. Offices and showroom are fitted with heated/chilled ceilings.
The north of the hall is accessed via a partially covered delivery area.
The south side, beneath the offices, will feature parking facilities and greened space.
In the west, a sizeable scarped drainage basin has been created to handle rainwater.
Geothermal energy, drainage basin, chilled and heated ceilings, deep foundations